Town of Clifton Park

Highway Department

 
What follows is a list of all areas that have been cleaned up as of this morning.
 
Completed South of Route 146:
- Crews Continue in Clifton Knolls, as it was the heaviest of areas, completing the Beechwood, Hemlock sections and working into Valencia section.
 
Completed North of Route 146:
- Crews have finished the North and South neighborhoods on Ushers Road, including Country Knolls, Ashley Section, VannWyck Estates, Knollwood Hollow.
 
- Cleanup is currently in Country Knolls West.
- A fourth crew is picking up in Country Knolls South, working from Woodstream West toward Twinbrook.
- Cleanup will be moving south in Country Knolls South.
State and County Roads:
- Once neighborhoods are completed, Crews will begin work on County and State roads.
 
All pickups are weather dependent. If weather does not cooperate, the Highway Department will be involved in snow and ice removal and will not be picking up brush that day.
 
We will have two crews going neighborhood by neighborhood. Please look back to the town’s website for updated information and details.
 
Please advise contractors that this is not a spring cleanup, but for storm debris only.
We will update which neighborhoods and roads have been completed to the best of our ability.